EV Charging for Apartment Body Corporates in NZ: A Practical Guide

By the Azraa EV team··9 min read
evchargingapartment

If you sit on a body corporate committee, EV charging requests are becoming one of the more common — and more contentious — items on the AGM agenda.

Get an instant price for this

If you sit on a body corporate committee, EV charging requests are becoming one of the more common — and more contentious — items on the AGM agenda. Getting a policy in place before the requests pile up saves months of ad hoc decision-making later. Here's a practical framework for body corporates dealing with EV charging in NZ apartment and unit-title buildings.

Why "wait and see" doesn't work

Body corporates that deal with EV charger requests one at a time, in the order they arrive, tend to run into the same problem: the first owner who asks gets a bespoke, informally approved solution, and by the third or fourth request the building's spare electrical capacity is gone, forcing a much more expensive supply upgrade that later owners feel they're unfairly funding. Setting a policy before you have more than one or two requests avoids this entirely.

What the Unit Titles Act actually requires

Installing a dedicated EV charger usually involves either altering common property, by running new cabling, or, less commonly, an exclusive use arrangement over part of the common property. Under the Unit Titles Act 2010:

  • Minor alterations to common property can often be approved by ordinary resolution, a simple majority, at a general meeting or, in some buildings, by the body corporate committee if it has delegated authority.
  • More significant changes, particularly anything affecting the building's shared electrical infrastructure or requiring a new easement or exclusive use area, typically require a special resolution, a higher threshold commonly around 75%, which takes more lead time and member engagement to secure.

The exact threshold and process depend on your building's body corporate rules and the specific nature of the work, so get advice from a body corporate manager or lawyer experienced in unit titles before assuming a straightforward majority vote is sufficient.

Get an electrical capacity assessment early

Before approving any individual charger installations, commission a qualified electrical engineer to assess the building's spare capacity and produce a report on how many EV chargers the existing supply can support before an upgrade is needed. This typically costs $1,800-$3,600 for a mid-size apartment building but pays for itself by giving the committee an objective basis for decisions, rather than approving requests reactively and discovering a capacity problem only when the fourth or fifth owner's installation trips the building's main supply.

Three common policy models

  1. Individual metered circuits. Each owner funds their own dedicated circuit and charger, metered separately so charging costs sit on their own power account. Fairest for cost allocation, but requires enough spare capacity for each installation and can get expensive per owner in buildings with long cable runs from the switchboard.
  2. Shared infrastructure, pay-per-use. The body corporate funds a shared upgrade — new distribution board capacity, conduit runs to car park zones — once, and individual owners then pay a smaller connection fee plus metered usage. This spreads the large capacity-upgrade cost across all future EV owners rather than making the first mover absorb it, but requires body corporate capital or a special levy upfront.
  3. Capped communal chargers. A small number of shared chargers in visitor or communal car park areas, booked via a roster or booking app, funded from the body corporate's general operating budget. Works for buildings with low EV uptake so far, but doesn't scale well once more than a handful of residents own EVs.

Cost apportionment is the most contentious part

Owners without EVs, and no plans to buy one, understandably resist body corporate funds being spent on infrastructure they won't use. The fairest approaches we've seen work in practice either isolate EV infrastructure cost to an opt-in special levy paid only by participating owners, or treat a base electrical capacity upgrade as a building-wide asset improvement, similar to lift or fire system upgrades, funded from the long-term maintenance plan, while individual connection and metering costs stay with the EV owner specifically.

EECA and lines company support

Multi-unit developments installing shared EV charging infrastructure may be eligible for co-funding support through EECA programmes from time to time, and local lines companies sometimes offer streamlined connection processes for known multi-unit charging upgrades. Programme availability changes, so it's worth a body corporate manager checking current options before the committee assumes the full cost falls on owners.

Insurance and liability questions worth raising early

Body corporates should also confirm how a dedicated EV charger installation interacts with the building's existing insurance policy, particularly around fire risk from charging equipment and who's liable if a fault in a shared circuit damages a resident's vehicle or the building itself. Most insurers are comfortable with a professionally installed, certified charger on a correctly rated circuit, but it's worth getting written confirmation from the body corporate's insurer before approving installations at scale, rather than assuming existing cover automatically extends to new EV-specific electrical work.

Building the policy document

A workable body corporate EV charging policy should cover: the approval process and required resolution type, who pays for what — installation, metering, ongoing capacity — a technical standard for approved chargers and installers to avoid inconsistent, poorly installed circuits, and a process for reviewing capacity as EV uptake in the building grows. Putting this in place before the fifth or sixth owner asks turns a recurring point of conflict into a routine administrative process, which is a better outcome for every apartment owner, EV driver or not.